()is a process of monitoring the status of the project to update the project costs and manage changes ti the cost baseline.
A、Plan Cost Management
B、Estimate Costs
C、Determine Budget
D、Control costs


相關試題

72題: is the extension of internet connectivity into physical devices and everyday objects.Embedded with electronics,internet connectivity and other forms of hardware (such as sensors), these devices can communicate and interact with others over the Internet ,and they can be remotely monitored and controlled.
A、Cloud Computing
B、Internet of things
C、Block Chain
D、Artificial Intelligence
答案解析與討論:www.rgjtff.live/st/4107710057.html

73題: is a process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
A、 Develop Project Charter
B、Manage Project Knowledge
C、Monitor and Control Project work
D、Close project
答案解析與討論:www.rgjtff.live/st/4107824333.html

74題: ()is a process of developing a detailed description of the project and product
A、collect requirements
B、Definition scope
C、validate scope
D、Control range